What does your peak
demand really cost?

A single 15-minute peak can double your annual grid charges — for the entire year. This calculator shows you what your current peak demand costs and how much you could save through automatic peak load management.

4 inputs
Live calculation
Based on real network tariffs

Your Details

Voltage Level Demand charge pre-filled
Measured Annual Peak Demand 800 kW
kW

Shown on your electricity bill as "Annual demand measurement" or "Maximum power"

Typical Operating Load 450 kW
kW

Your average load during normal operations

Demand Charge (network tariff)
€/kW·a

Take this value from your network use-of-system invoice or your network operator's price schedule

Metering Equipment affects investment estimate
Capacity costs

Annual capacity costs = annual peak demand × demand charge. This is based on the network demand charge levied on the highest measured 15-minute average power of the year.

Additional costs from peak demand

Additional costs = (peak demand − operating load) × demand charge. This amount shows how much more you pay compared to your typical load — caused by short-term peaks.

Savings potential

Experience shows that automatic peak load management can eliminate 35–45% of the difference between peak and normal load. The calculator uses 40% as a conservative estimate. Actual savings depend on the load profile and the controllable consumers available.

Investment estimate

The investment is derived from the peak demand: the kW magnitude determines the typical number of metering points (main meter + controllable loads). Costs: 697 €/metering point incl. hardware (350 €/point if metering already exists) plus one-off project set-up (1,000–8,000 € depending on size).

Payback period

Net investment (after BAFA grant) ÷ annual savings potential = payback period in months.

Your Peak Demand Analysis

Live
Additional costs from peak demand
38,500 €/year
That you pay above your normal operating load

Load comparison & capacity costs

Typical Operating Load
450 kW 49,500 €/a
Current Peak Demand (what you are charged on)
800 kW 88,000 €/a
With Peak Management (achievable)
660 kW 72,600 €/a
Savings potential through peak load management
15,400 €/year
Reduction of ~140 kW peak demand
Current capacity costs / year
88,000 €
Estimated investment
(EMS set-up + software + hardware)
~18,500 €
BAFA grant BEW Module 3
(45% · small enterprises)
~8,325 €
Net investment after grant
~10,175 €
Payback period
approx. 8 months
012 mo.24 mo.36 mo.+
Realise your savings potential →

* Estimate based on typical load profiles and a conservative reduction potential of 40% of the peak demand differential. Actual savings depend on the load profile, plant structure, and available controllable loads.

How your peak demand
determines your annual bill

The 15-minute principle

Single peak
in the year
12×
Months of elevated
capacity costs

Your network operator measures your power in 15-minute intervals. The highest value of the entire year determines your demand charge — for all 12 months. A peak caused by several machines starting simultaneously can permanently increase your grid bill.

Simultaneous start-up

When multiple motors, compressors, or furnaces start at the same time, short-term inrush peaks occur — often 3–6 times the rated current.

Shift start & rush hours

At shift changeovers, many systems are often activated at the same time. Without control, a typical "morning peak" emerges that drives up the demand charge.

Unplanned events

Emergency runs, catch-up production after downtime, or loss of PV feed-in can unnoticed create annual peak demand events.

Automatic peak load management
with Alligator

Alligator monitors your load in real time and intervenes automatically before a cost-driving 15-minute peak occurs.

Real-time power monitoring

Second-by-second measurement of total power at the grid connection point. The system continuously calculates how far you are from the 15-minute rolling average.

Predictive intervention

Before a peak occurs, controllable consumers (HVAC, pumps, EV charging, process heat) are automatically delayed or briefly reduced.

Verification & reporting

Every avoided peak demand is documented. Each month you see by how many kW your peak was reduced — and what that has concretely saved.

Peak Demand & Demand Charges

What is the demand charge and why is it so critical?

The demand charge (also: capacity element of network use-of-system charges) is a part of your grid bill levied not on energy consumption (kWh) but on the highest measured power demand (kW). The network operator measures your load in 15-minute intervals and multiplies the annual maximum by the demand charge in €/kW·a. Typical values: low voltage 80–150 €/kW·a, medium voltage 40–90 €/kW·a. The problem: a single peak determines the costs for the entire year.

Does the demand charge apply to every company size?

The demand charge applies to all customers with a half-hourly (registering) meter (RLM customers). These are generally businesses with an annual consumption of around 100,000 kWh or more (from approximately 11 kW connected load) — or smaller operations that opt in. Many SMEs are unaware that a significant portion of their electricity bill consists of the capacity element — often 20–40% of network costs.

How much peak demand reduction is realistic?

This depends strongly on how many controllable consumers are present in the facility (HVAC, pumps, compressors, EV charging infrastructure, process heat). In practice, businesses using Alligator typically achieve a reduction in annual peak demand of 15–40% compared to uncontrolled operation. The calculator uses 40% of the difference between peak and normal load as a conservative estimate.

Can controllable consumers be managed automatically?

Yes — Alligator communicates via standard protocols (Modbus, M-Bus, OPC-UA, BACnet) directly with PLC controllers, building automation systems, and smart switching actuators. Intervention occurs fully automatically, prioritised according to rules you define (e.g. reduce HVAC before process heat) and can be manually overridden at any time.

Can peak load management disrupt the production process?

No — the rule set is defined together with you. Production-critical plant is excluded from peak load management. Interventions only affect non-critical consumers (heating, cooling, charging infrastructure) and always remain within predefined tolerance limits. The system intervenes only when a peak is imminent — and switches back immediately.

Eliminate peak demand,
reduce capacity costs permanently

In a free initial consultation, we analyse your load profile and show you which concrete savings are realistically achievable.

Free initial consultation → Calculate total energy costs →